Press Release

Balfour Beatty awarded £24m power line in Scotland

9 September 2013

UK

Balfour Beatty, the international infrastructure group, has been awarded a £22m contract with SSE to construct a replacement overhead electricity line in the North of Scotland.

The project involves the construction of a 132kV power line connecting substations at Beauly and Mossford in the Highlands. The 26km route will replace two existing lines, which Balfour Beatty will dismantle as part of the programme of works.

Enabling works, such as access roads, began in August and the project is expected to be complete in 2015.

The replacement of the existing Beauly to Mossford line is a part of ongoing investment in the electricity transmission network in the north of Scotland.  The growth of renewable generation has been significant in recent years and is driving the need for transmission reinforcement.

Neil Kirkby, Managing Director, Balfour Beatty – Power Transmission & Distribution, said:
“Power is an important strategic market for Balfour Beatty, both in the UK and internationally and we are delighted to be continuing our relationship with SHE Transmission through this important infrastructure project.

“Scotland offers many unique challenges to our operations, including inhospitable terrain, unpredictable weather conditions and sensitive environments. Our teams have a wealth of experience of working within these constraints whilst delivering other power projects in the area, and lessons learnt from these operations will be key in the successful completion of the Beauly to Mossford line.”

The new contract is one of several major power infrastructure projects being carried out by Balfour Beatty’s Power Transmission & Distribution team in Scotland.

Also on behalf of SSE in the Highlands, the company is constructing the Beauly to Denny overhead line project, a 227km overhead line which is the largest of its kind in the UK, and undertaking the Beauly Blackhillock Kintore project, which involves refurbishing and reinforcing 372 electricity towers along a 157km route. Balfour Beatty is also carrying out the refurbishment of over 100km of power lines in Southern Scotland for Scottish Power Energy Networks.

Find out more about our Services Division

Media enquiries to:
James Merrylees
Media & PR Manager
Balfour Beatty Services Division
+44 (0)114 232 9562
+44 (0)7967 689032
james.merrylees@bbusl.com 

Notes to editors:

Balfour Beatty (Balfour Beatty (www.balfourbeatty.com) is an international infrastructure group that delivers world class services essential to the development, creation and care of infrastructure assets; from finance and development, through design and project management to construction and maintenance.

Our businesses draw on more than 100 years of experience to deliver the highest levels of quality, safety and technical expertise to our clients principally in the UK, the US, Southeast Asia and the Middle East. We continue to develop our business in key growth markets in South Africa, Australia, Canada, Brazil and India.

With proven expertise in delivering infrastructure critical to support communities and society today and in the future, our key market sectors include transportation (roads, rail and aviation), power and energy, mining, water and social infrastructure such as hospitals and schools.

Balfour Beatty employs 50,000 people around the world. 